Srinagar, Nov 16 (KNO): The Jammu and Kashmir government has approved Rs 22.71 crore for the construction of a Mini Secretariat along with an Integrated District Disaster Management and Mitigation Centre at Batamaloo in Srinagar, paving the way for the revival of a project that has remained stalled for several years.
As per Government Order No. 57-JK (Rev) of 2026, issued by the Revenue Department, administrative approval has been granted for an estimated expenditure of Rs 2,271.07 lakh. The project cost has been assessed on the basis of estimates vetted by the Engineer-in-Chief, Public Works (R&B) Department.
The proposed facility will serve as an administrative hub while also housing infrastructure for district-level disaster preparedness, management and mitigation.
According to the news agency—Kashmir News Observer (KNO), the project dates back to October 2017, when the proposal for establishing a Mini Secretariat at the erstwhile General Bus Stand in Batamaloo was taken up during a District Development Board meeting. Its foundation stone was subsequently laid by the then Chief Minister Mehbooba Mufti in January 2018.
Initially, the complex was planned to accommodate multiple government offices under one roof, with the objective of improving public service delivery and reducing the need for people to visit different offices spread across Srinagar.
However, its execution remained delayed due to financial and administrative issues.
The matter was brought up in the Legislative Assembly in March 2025, when Education Minister Sakina Itoo informed the House that Rs 9.82 crore had already been spent on the project. She said the original technically vetted cost stood at Rs 48.23 crore, while a revised Detailed Project Report amounting to Rs 80.26 crore had been submitted by the executing agency and was under consideration. The pile foundation work had also been completed.
The project received fresh attention in September 2026 after Chief Minister Omar Abdullah reviewed stalled projects under the Revenue Department and directed concerned departments and district administrations to resolve pending issues and initiate work on languishing and new Mini Secretariat projects within a month. The Batamaloo project was among those reviewed.
Its proposed development also forms part of the broader urban planning vision under the Srinagar Master Plan-2035, which envisages shifting several government offices from central Srinagar to Batamaloo to ease congestion in the city.
Among the offices proposed for relocation are those of the Forest Department, Old Assembly Complex, Old Secretariat Complex, Divisional Commissioner, Deputy Commissioner, Directorate of School Education Kashmir and Agriculture and Horticulture departments.
The Master Plan also proposes shifting the Civil Secretariat to Nowgam along the National Highway Bypass, although a final decision regarding relocation of the existing Secretariat has not been established.
The latest government order has specified a set of conditions for executing the project, including compliance with procurement procedures, availability of funds, technical sanction, statutory permissions and environmental requirements.
It has also made provisions for third-party quality assessment, geo-tagging of construction activities and photographic and videographic documentation to monitor progress.
The executing agency has been directed to complete the work within the prescribed timeline while avoiding cost escalation and delays. Regular progress reporting through the PROOF App and appropriate project-monitoring software has also been made mandatory to ensure transparency and effective monitoring—(KNO)