Srinagar, Nov 28 (KNO): In the Kashmir valley, power consumers are bearing the cost of infrastructure gaps they did not create. Forced outages stretching beyond the revised curtailment schedule are hitting metered and non-metered areas alike, in grids where smart meters and insulated cables remain incomplete— leaving residents to absorb the consequences as a collective burden.
An official informed the news agency—Kashmir News Observer (KNO) that in any area wherein smart meters or insulated cables are not installed, they also face forced power cuts beyond the revised curtailment schedule.
“Ideally in smart metered areas, there should have been no forced power cuts beyond the revised curtailment schedule,” the official said.
It also said that “Under the catchment area of some power grids, smart meters and cables have been installed at some places but some areas are still on flat rate.”
“During the time of limited power supply, the grid faces forced power cuts and thus all of the consumers, be it metered or non-metered, face collective burden in terms of forced power cuts,” the official said.
It also said, “If the forced power outages beyond the revised curtailment schedule is not enforced in metered areas, the non-metered areas who already are facing long scheduled power cuts may face extra outages.”
Pertinently, the Power Development Department (PDD) in October announced a new Load Curtailment Plan (LCP) for consumers in the Kashmir division, which will include extra hours of load shedding in the high AT&C losses.
According to the new LPC, the consumers will face a daily power curtailment of 8 hours in the areas having Aggregate Technical and Commercial (AT&C) above 65 percent.
It also said that the areas having AT&C losses between 40.5-65 percent will face power curtailment of 6 hours daily.
Furthermore, the new LPC said that the areas having AT&C losses in between 15 to 40.5 percent will face curtailment of 3 hours daily. However, there will only be 0.5 hours of curtailment in the areas having AT&C losses from 0-15 percent.
Earlier the officials of PDD had informed KNO that there are 1335 KV feeders under the jurisdiction of KPDCL. “In previous LCP there were only 129 feeders with round the clock power facility but under the new LCP, 85 new feeders have been added for 24*7 electricity supply because they have AT&C losses of less than 20 percent.”—(KNO)